A new sewer rising main will be constructed in the road reserve of five streets as part of the GV Link Enterprise Park project.
The affected streets are O’Brien, Ann, Morrell and Alexander Sts, as well as the Echuca Rd service lane.
Lay-down areas will be established on Echuca Rd and O’Brien St.
At these locations, material and plant will be stored overnight and fenced off for security, and pipe welding will occur during the day.
The area where the sewer works will take place.
The works will start on Monday, September 22 and are expected to be completed by Friday, November 14.
The works will be undertaken between 7am and 6pm from Monday to Friday, and 7am to 1pm on Saturday, weather permitting.
Traffic management, including road closures, speed limits and traffic diversions, will be in place during this time.
Access to local and nearby businesses and properties will remain open.
Motorists are advised to follow signage and take care when travelling in the area.